The process is as follows:
Process
- Assemble street captains for street blocks
- Hold a public meeting – Aug 2018
- Collect 70% of the deposit for all the erf (Approx R2000 per erf)
- Initiate the traffic impact study and prepare application to council (approx 2 months)
- Council Approval
- Collect 2nd Deposit
- Construction bids
- Construction
Approx time table
- Get 70% support from residents and payment end June 2018
- Traffic Impact Study and Application drawn up July/Aug/Sep
- Application to Council by Dec 2018
- Permission by Council – ±September/October 2019
- Construction – ±November 2019
- Operational – ±December 2019
Council Requirements
- 67% Support by owner
- Traffic Impact Study
- Formal Application
- Application Fee
- All departments to approve
- SLDT give principal approval
- 40 days advertising for objections
- 58 requirements – way leave approval
- 2 years re-application