Depending on the support the initiative received – we should meet these dates. Lets do this Waterkloof.
20 March – Wayleave applications were submitted
14 April – Advertise for Construction & Guarding tender
5 May – Tenders close
24 May – Start construction
June – Road Marking & Signage
July – August – Construction of permanent closures and sliding gates
September – November – Construction of manned gates (Start with 12hr manned gates)
1 October – Start operating first gates
1 December – full operation