Key dates for 2021

Depending on the support the initiative received – we should meet these dates. Lets do this Waterkloof.

20 March – Wayleave applications were submitted

14 April  – Advertise for Construction & Guarding tender

5 May  – Tenders close

24 May – Start construction

June – Road Marking & Signage

July – August – Construction of permanent closures and sliding gates

September – November – Construction of manned gates (Start with 12hr manned gates)

1 October – Start operating first gates

1 December – full operation